5.1.8. Asphalt Shingle Roof Mounting
a) Apricus recommends EcoFasten Solar flashings that can easily
be slipped under 3 tab composition roofing and secured to the roof
framing member. The frame front tracks can be attached to the
flashing bracket with a U-foot (available from Apricus).
Image to the right shows the standard EcoFasten Z shaped bracket.
b) Unistrut can be mounted with the same method if installing an
adjustable angle kit with a track frame. This is a clean, reliable
method for mounting to asphalt shingle roofs.
For more information visit http://www.ecofastensolar.com
5.1.9. Tiled Roof Mounting
a) For tiled roofs, use a flashing designed for solar mounting such
as the one shown to the right from QuickMount PV. This style can
be molded to the shape of the tiles and forms a strong and
watertight flashing.
For more information visit http://www.quickmountpv.com
5.2. Mounting on Suitable Angle Pitched Roof (Standard
Frame)
Refer to Appendix 1 for assembly diagram.
5.2.1. Installation Planning
a) Carefully plan the location of the collector frame and plumbing pipes
in order to align with the roof framing members and develop the shortest
pipe run possible to the storage tank. Any penetrations in the roof or
building shell must be sealed with standard roofing materials and/or
appropriate sealants to avoid leaks.
5.2.2. Positioning Manifold
a) Securing to Roof: The manifold and bottom track can slide left and
right in relation to the standard frame channels, so there is some
flexibility when selecting the location. The standard frame channels should be located so that they lay flat,
are parallel with one another and, if possible, aligned with the roof rafters. If the frame cannot be aligned
with the roof rafters, a rafter upgrade may need to be perform by adding additional wood to the framework.
Consult an engineer to ensure roof designs and rafter upgrades meet structural requirements.
b) Manifold and Bottom Track Alignment: Ultimately, each Evacuated Tube will be installed with the Heat
Apricus Solar Collector Installation & Operation Manual - USA
Copyright © 2011 – Apricus Inc Doc: A7-05.4.12-PB Page 36 of 129